SOURCE: Davis Contractors Ltd v Fareham Urban District Council [1956] UKHL 3; [1956] AC 696; [1956] 2 All ER 145 URL: https://www.bailii.org/uk/cases/UKHL/1956/3.html ACCESSED: 16 September 2026 (BAILII text opened in a browser on the user's Mac; page text saved verbatim) [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] United Kingdom House of Lords Decisions You are here: BAILII >> Databases >> United Kingdom House of Lords Decisions >> Davis Contractors v Fareham Urban DC [1956] UKHL 3 (19 April 1956) URL: https://www.bailii.org/uk/cases/UKHL/1956/3.html Cite as: [1956] UKHL 3, [1956] AC 696, [1956] 2 All ER 145 [New search] [Buy ICLR report: [1956] AC 696] [Help] JISCBAILII_CASE_CONTRACT Die Jovis, 19° Aprilis 1956 Parliamentary Archives,HL/PO/JU/4/3/1036 Viscount Simonds Lord Morton ofHenryton Lord Reid Lord Radcliffe Lord Somervellof Harrow HOUSE OF LORDS DAVIS CONTRACTORS LIMITED v.FAREHAM URBAN DISTRICT COUNCIL 19th April, 1956. Viscount Simonds MY LORDS, This appeal arises out of arbitration proceedings to which the parties werethe Appellants Davis Contractors Limited, a firm of building contractors,and the Respondents the Fareham Urban District Council. On the 9thJuly, 1946, the parties had entered into a building contract whereby theAppellants agreed to build for the Respondents 78 houses at GudgheathLane, Fareham, in the county of Southampton within a period of eightmonths for a sum of £85,836. For various reasons, the chief of them the lack of skilled labour, the worktook not eight but twenty-two months. The Appellants were in due coursepaid the contract price which, together with stipulated increases and adjust-ments, amounted to £94,424. They contended, however, that owing to thelong delay the contract price had ceased to be applicable and that they wereentitled to a payment on a quantum meruit basis. The Appellants put their claims on alternative grounds (a) that the contractprice was subject to an express overriding condition contained in a letterof the 18th March, 1946, that there should be adequate supplies of labourand material and (b) that the contract had been entered into on the footingthat adequate supplies of labour and material would be available to completethe work within eight months, but, contrary to the expectation of bothparties, there was not sufficient skilled labour and the work took twenty-twomonths, and that this delay amounted to frustration of the contract. Itwas conceded by the Respondents that, if the contract was frustrated asalleged, the Appellants were entitled to a further sum upon the basis of aquantum meruit. With this aspect of the case which might have presentedsome difficulty your Lordships will not be troubled. These two groundsof claim have persisted through the long course of these proceedings whichhave included a prolonged hearing before an arbitrator, an award in theform of a special case, a hearing of the case by the Lord Chief Justice,an appeal to the Court of Appeal, a reference back to the arbitrator, asupplemental award by him, a further hearing by the Court of Appeal,and an order of that Court rejecting the Appellants' claim. My Lords, with the first ground of claim I will deal very briefly. I amin full agreement with the opinion of Lord Justice Parker on this partof the case, which will be elaborated by my noble and learned friend, LordRadcliffe. The Appellants' letter of the 18th March. 1946, to which I havereferred, was a covering letter in which, while enclosing their tender preparedin accordance with the Respondents' Bills of Quantities and Specifications,they made a number of statements about the basis of that tender. Thematerial statement was as follows: " Our tender is subject to adequate sup-" plies of material and labour being available as and when required to" carry out the work within the time specified ". It is possible that, if thisletter had been followed by an immediate acceptance, the parties must havebeen deemed to enter into a contract which contained some such term, thoughits precise content and effect would have been extremely difficult to define.But that is not what took place nor what might be expected to take place.On the contrary, there were negotiations following the tender and theseresulted in the formal agreement of the 6th July, which did not incorporatethe letter of the 18th March. It would as it appears to me be contraryto all practice and precedent to hark back to a single term of precedingnegotiations after a formal and final agreement omitting that term has beensigned. The reference to the letter in an appendix to the tender is clearlyconfined to the matter with which that appendix dealt, namely the so-called" escalator" clause of the conditions of contract. 2 The second ground of claim demands more serious consideration notbecause it has any intrinsic merit but because it has acquired from thecourse of the proceedings a certain specious validity. I cannot avoid reciting to your Lordships some of the findings of theArbitrator. After stating that the site was handed to the Appellants andwork was begun on the 20th June, 1946, and completed on the 14th May,1948, the Arbitrator proceeded thus: " (6) At the time of entering into the said agreement the Claimants" and the Respondents anticipated that there would be available in the" building industry a sufficient labour force and a sufficient supply of" materials to enable the work specified in the agreement to be carried" out substantially within the time stipulated in the agreement. " (7) The conditions in which the work had to be carried out were" different from those anticipated by the Claimants and the Respondents"in that: " (a) At all times there was a serious shortage of skilled labour" in the industry and the Claimants were unable to obtain an" adequate supply of such skilled labour ; " (b) There was difficulty in obtaining adequate supplies of bricks," timber and plumbers' goods ; " (c) There was an adequate supply of unskilled labour in the" industry but not at all times within the locality of Fareham where" the Claimants were required under the General Conditions of" Contract to recruit such labour unless the importation of labour" from elsewhere were specially sanctioned by the Respondents. " (8) As a result of the said shortage of labour and materials the" Claimants were unable to complete the work within the time specified" in the agreement and the Respondents accepted the position and" allowed the work to continue until finally completed on 14th May," 1948, without serious objections by the Respondents. " (9) As a result of the longer time taken to complete the work the" Claimants incurred additional expense and the actual cost to them" of carrying out the contract was £115,233 14s. 0d. The Claimants" have been paid by the Respondents the sum of £94,424 17s. 9d." He then referred to the Appellants' claim for further payment in respectof their additional cost and expense, which he found to have been partlydue to the circumstances set out above, over which they had no control,and to exceptional weather conditions and partly due to matters for whichthey were themselves to blame, and came to the conclusion that the sumof £17,651 13s. 1d. (which was afterwards slightly reduced) represented theamount of additional cost properly and unavoidably incurred by them. Hethen stated the submission of the Appellants on this point, viz.: that thecontract was entered into on the " basis" that adequate supplies of labourand materials would be available at the times required and that becausethey were not so available the " footing " of the contract was removed andthat they were entitled to be paid on the basis of a quantum meruit. Thequestion of law stated by him which was intended to cover this point wasput baldly thus " Whether the Claimants " [the Appellants] " are entitled to be" paid any sum in excess of £94,424 17s. 9d. already paid them? " Upon the matter coming before the Court the Lord Chief Justice was ofthe opinion which your Lordships have rejected that the letter of the 18thMarch, 1946, was incorporated in the contract and upon that basis wasfurther of opinion that there was an implied promise by the Respondentsto pay a further reasonable sum if the conditions of the letter were notsatisfied. The learned Judge referred to the case of Bush v. WhitehavenTrustees, which must be discussed later, but observed " I do not think that" it is necessary to go as far as that because I do not think that it is a destruc-" tion of the whole foundation of the contract". An appeal was taken to the Court of Appeal. Upon the question ofthe letter of 18th March being incorporated in the contract the Court,though no order to that effect was drawn up, expressed a view adverse 3 to the Appellants, but upon the alternative ground of claim, with whichI am now concerned, thinking that the findings of the arbitrator wereinadequate referred the case back to him with this direction " that the" said Arbitrator may make further findings of fact for the information" of this Court relevant to the application of the principle in the case of" Bush v. Whitehaven and the contentions of the parties on this issue. The" Arbitrator to state his own conclusions on the contentions of the parties" if he intends his award to be a final award ". My Lords, I do not find it easy to interpret this direction. The case ofBush v. Whitehaven Trustees, which is reported only in Hudson on BuildingContracts, if it can be said to embody any principle, illustrates an earlystage in the development of the doctrine of frustration which has since beenthe subject of many decisions in this House. And it was, I think, to thisissue that the contentions of the parties and the further findings of theArbitrator were directed. Thus, while the Appellants repeated their formercontention that, because adequate supplies of labour and material werenot available, the footing of the contract was removed, the Respondentscontended that " in any event the footing on which the contract was agreed" was not so changed that the contract could be declared or treated as" void or the Claimants be entitled to payment on a quantum meruit" and" That any claim on a quantum meruit basis was precluded by reason of" the conduct of the parties after a claim for additional payment was first" intimated by the Claimants " and " That the Respondents so far from" allowing the Claimants to continue work on a different basis consistently" maintained that the contract was still applicable ". The Arbitrator then stated (inter alia) the following question of law" Whether the Claimants are entitled to be paid any sum in excess of the" £94,424 17s. 9d. already paid them, namely on a quantum meruit, by" reason of: (a) the footing upon which the contract was made having been" so changed in the course of its execution that its provisions no longer" applied or (b) an implied term in the contract that it ceases to bind in the" circumstances as found ". Having been asked to state his own conclusions he further found thatboth parties entered into the contract on the basis that adequate suppliesof labour and material would be available at the times required, that suchsupplies were not so available and that, as the duration of the work wasunavoidably extended from a period of eight months to one of twenty-twomonths, the footing of the contract was removed. I do not think it necessaryto state all his conclusions but it is proper to add that, for reasons whichare set out, he found that " the footing of the contract was so changed that" it became void and the Claimants are entitled to a fair and reasonable" price for the work they have done ". I do not refer to his findings aboutthe conduct of the parties except to say that at an early stage they wereat issue, the Appellants making and pressing a claim for additional pay-ment which the Respondents steadfastly resisted. Giving effect to his ownconclusions the Arbitrator found that the Appellants were entitled to bepaid a further sum of £17,258 13s. 1d. Now the matter came back to the Court of Appeal, which was not con-stituted as on the former occasion. The alternative grounds of claim wereagain fully argued. The first ground, that of the incorporation of the letterof the 18th March in the contract, was rejected either because it was heldnot to be incorporated or because, even if incorporated, it had not theeffect for which the Appellants contended. Upon this I will say no more. The second ground of claim remains, and upon this the learned Judgesof the Court of Appeal were unanimously against the Appellants andthey were, in my opinion, clearly right. If the matter had in the first instancecome before a Court of Law which after finding the facts as found by theArbitrator had then to consider the law applicable to those facts, therecould only have been one answer. The Lord Chief Justice was, in myopinion, stating the obvious when he said in the passage that I have cited" I do not think it is a destruction of the whole foundation of the contract".| 4 The doctrine of frustration of a contract (for it is that doctrine and nothingelse which must be invoked) has never been applied or, so far as I amaware, been sought to be applied to such a case unless indeed Bush v.Whitehaven was one. The contract was for completion of certain work ineight months: the contractors made their tender in the expectation thatthey would be able to do the work in the time and made a price accordingly.It may then be said that they made the contract on the " basis " or onthe " footing " that their expectations would be fulfilled. Nor presumablywere the expectations, or at least the hopes, of the Respondents in anyway different. Let it be said, then, of them, too, that they contracted uponthe same basis or footing. But it by no means follows that disappointedexpectations lead to frustrated contracts. I do not propose to revive thecontroversy about the juridical basis of the doctrine of frustration. If itrests on an implied term of the contract to the effect that the parties willnot be bound if a certain event happens or does not happen, I can seeno ground for saying that such a term must be implied in this contract.If it is permissible to judge by the event, it is clear that the parties wouldnot have agreed on any such term. I pause to observe that it is not enoughto say that in the event of something unexpected happening some term mustbe implied: it must be clear also what that term should be. In such acase as this I can see no reason for supposing that the parties wouldhave agreed either at what moment the frustrating event was to be deemedto happen or what was to be the position when it in fact happened. Equally,if, as is held by some, the true doctrine rests not on an implied term ofthe contract between the parties but upon the impact of the law on asituation in which an unexpected event would make it unjust to holdparties to their bargain, I would emphasise that in this aspect the doctrinehas been and must be kept within very narrow limits. No case has beencited in which it has been applied to circumstances in any way comparableto those of the present case. It is sufficient to ask when in the courseof this twenty-two month contract that unexpected disruptive event happenedwhich put an end to it. " Rights ", said Lord Sumner in Bank Line, Limitedv. Arthur Capel & Company [1919] AC 435, "ought not to be left in" suspense or to hang on the chances of subsequent events ". It is whollyinconsistent with this, as I think, fundamental condition that a buildingcontractor should without intermission work upon his contract over a periodwhich by much or little exceeds the contract time and at the end of it say,as the Appellants say here, " A twenty-two month project is not an eight" month project " or less formidably " An expenditure of £111,000 is not an" expenditure of £94,000 ", " therefore the original contract must be regarded" as frustrated and for all the work that has been done we must be paid" not the contract price but upon the basis of a quantum meruit". My Lords,I say it with all respect to the arguments of learned Counsel but it appears tome that that is to make nonsense of a doctrine which, used within its properlimits, serves a valuable purpose. But, it was urged, this case cannot be regarded in the manner that Ipostulated. There are the findings of the Arbitrator, a man experiencedin the matter of building contracts, and they should not be set aside. I willsay at once that the Arbitrator has clearly done his work with great careand skill. But his findings involve a blend of law and fact and, deliberatelyusing the words that he has chosen, " basis" and " footing", I can seeno justification for a conclusion of law that the contract was frustrated. It remains to say something about the case of Bush v. Whitehaven Trusteeswhich has loomed so large in the earlier stages of this case and. in theargument before this House. I must say for myself that I find it an extremelypuzzling case and, if it had been a decision of this House and thereforebinding on us, I should have felt grave difficulty about it. But two thingsmay be said: first it is not binding on us; secondly in so far as it is anauthority on the law of frustration for which purpose alone I conceive itto have been cited, it must be read in the light of the numerous decisionsof higher authority which have since been given. I am not satisfied thatit can be supported on the ground suggested by Lord Justice Denning nor, 5 on the other hand, do I say that the decision is a wrong one. But I doemphatically say that it cannot in the light of later authority be used tosupport the proposition that where, without the default of either party,there has been an unexpected turn of events which renders the contractmore onerous than the parties had contemplated that is by itself a groundfor relieving a party of the obligation he has undertaken. I agree withthe learned Lord Justice that that is the import of the decision of thisHouse in British Movietonews Ltd. v. London & District Cinemas Ltd., [1952]A.C. 166 and that it precisely covers this case. I would dismiss this appeal with costs. Lord Morton of Henryton MY LORDS, Two questions of law arise on this appeal: Was the letter of 18th March, 1946, from the Appellants to theRespondents, incorporated in the contract under seal which was enteredinto by the parties on the 9th July, 1946? Was that contract frustrated, with the result that the Appellants,who have erected 78 houses for the Respondents, are not bound to acceptthe contract price, but are entitled to a further sum of over £17,000,which the arbitrator has awarded to them? My Lords, in my opinion the letter of 18th March, 1946 merely formedpart of the negotiations between the parties which led up to the contractof 9th July and its terms were not incorporated into that contract. Thismatter is dealt with fully in the opinion which will be delivered by my nobleand learned friend, Lord Radcliffe, and I am content to say that I agree withhis reasoning and his conclusion. I can state quite briefly my views on the second question, since I understandyour Lordships are all of opinion, as I am, that the Court of Appeal reachedthe right conclusion. The Appellants contracted to complete 40 houseswithin six months, 70 within seven months, and all the 78 houses withineight months. It is agreed that the work started on the 20th June, 1946,and should, therefore, have been completed in February, 1947. In fact, theprogress of the work was delayed, because, as the arbitrator held, " adequate" supplies of labour and materials were not available at the times required ".Nevertheless, the Appellants went on with the work, without any actual inter-ruption, and completed it in a period of 22 months. They now contend thatthe contract was frustrated, and they rely on certain findings by the arbitrator,which have already been read, and on the decision of the Court of Appealin Bush v. Whitehaven, reported in Hudson on Building Contracts, fourthedition, volume 2, page 122. My Lords, it is clear that the Appellants are entitled to no more thanthe contract price, unless they can satisfy your Lordships that at some timethe contract of 9th July, 1946, came to an end, so that in continuing to erecthouses they were no longer working under that contract. I am not so satisfied.I agree with the observation of Morris, L.J. that " though the basis or footing" of the contract was removed in the limited sense that the anticipations of" the parties were not realised, the facts found do not require an implication" in the contract that it was to come to an end if these anticipations were" not realised ". It is, I think, impossible to hold that a contract has beenfrustrated unless it can be said " as and from such and such a date, at latest." the contract ceased to bind the parties ". In the course of the hearing Counsel for the Appellants were asked:" When do you say that the contract came to an end?", and they repliedthat they were unable to specify any time. I think that this answer wascorrect and inevitable, but it reveals the inherent weakness of the Appellants'case. 6 The facts in the case of Bush v. Whitehaven are very briefly stated in thereport, but I think it is clear that the judgments of the Court of Appeal inthat case were based upon the findings of the jury, and in particular the fifthfinding. The question put to the jury was: " Were the conditions of the" contract so completely changed, in consequence of the defendant's inability" to hand over the sites of the work as required, as to make the special pro-" visions of the contract inapplicable?", and the jury replied: " Yes ". Thisquestion was, I think, a question of law, or at least of mixed fact and law,but the Court of Appeal accepted the jury's answer, and on that footingheld that by 8th October, 1886, when the contractors got possession of therequired sites, the contract had ceased to exist. In my opinion Bush v.Whitehaven was a decision upon very special facts, which enabled the Courtto find that, although the contractors finished the work specified in thecontract, they were not working under the contract from 8th October, 1886,onwards. For this reason the case does not, in my opinion, assist theAppellants. I would add that since the decision in the case just cited, thedoctrine of frustration has frequently been considered in your Lordships'House, and for an authoritative exposition of the doctrine one should turnto the speeches in this House rather than to the judgments of the Court ofAppeal in Bush v. Whitehaven. I would dismiss the appeal. Lord Reid MY LORDS, The arbitrator has found in his supplementary award that " the footing of" the contract was removed ", and his reason for so finding is that " both" parties entered into the contract on the basis that adequate supplies of" labour and materials would be available at the times required " but thatadequate supplies were not available with the result that the duration of thework was unavoidably extended from 8 months to 22 months. It seems clear thathe has used the words " footing " and " basis " because the Special Case wasreferred back to him for further findings of fact relevant to the applicationof the principle in the case of Bush v. Whitehaven, and the contentions ofthe parties on this issue, and the parties used these words in their contentions.The Appellants' submissions as stated in the award are almost identical withthe arbitrator's findings, and the Respondents' submission is that the footingon which the contract was agreed was not so changed that the contract couldbe treated as void. This form of award gives rise to considerable difficulty.But I have some sympathy with the arbitrator: he may have found as muchdifficulty as I have in discovering " the principle in the case of Bush v." Whitehaven ". In order to determine how far the arbitrator's findings are findings of lawand therefore subject to review I think it is necessary to consider what is thetrue basis of the law of frustration. Generally this has not been necessary:for example, Lord Porter said in Denny, Mott & Dickson v. Fraser & Co,[1944] A.C. 265 at p. 281: " Whether this result follows from a true construc-" tion of the contract or whether it is necessary to imply a term or whether" again it is more accurate to say that the result follows because the basis" of the contract is overthrown, it is not necessary to decide ". These are thethree grounds of frustration which have been suggested from time to timeand I think that it may make a difference in two respects which is chosen.Construction of a contract and the implication of a term are questions of law,whereas the question whether the basis of a contract is overthrown, if notdependent on the construction of the contract, might seem to be largely amatter for the judgment of a skilled man comparing what was contemplatedwith what has happened. And if the question is truly one of construction Ifind it difficult to see why we should not apply the ordinary rules regardingthe admissibility of extrinsic evidence whereas, if it is only a matter of com-paring the contemplated with the actual position, evidence might beadmissible on a wider basis 7 Further, I am not satisfied that the result is necessarily the same whetherfrustration is regarded as depending on the addition to the contract of animplied term or as depending on the construction of the contract as it stands. Frustration has often been said to depend on adding a term to the contractby implication: for example, Lord Loreburn in Tamplin Steamship Co. Ltd.v. Anglo Mexican Petroleum Products Co. Ltd. [1916] 2 A.C. 397 at p. 404,after quoting language of Lord Blackburn, said: " That seems to me another" way of saying that from the nature of the contract it cannot be supposed" the parties, as reasonable men, intended it to be binding on them under" such altered conditions. Were the altered conditions such that, had they" thought of them, they would have taken their chance of them, or such" that as sensible men they would have said: ' If that happens, of course,"' it is all over between us"? What, in fact, was the true meaning of the" contract? Since the parties have not provided for the contingency, ought a" court to say it is obvious they would have treated the thing as at an end? ". I find great difficulty in accepting this as the correct approach because itseems to me hard to account for certain decisions of this House in this way.I cannot think that a reasonable man in the position of the seaman in Horlockv. Beal [1916] 1 A.C. 486 would readily have agreed that the wages payableto his wife should stop if his ship was caught in Germany at the outbreakof war, and I doubt whether the charterers in the Bank Line case couldhave been said to be unreasonable if they had refused to agree to a termthat the contract was to come to an end in the circumstances which occurred.These are not the only cases where I think it would be difficult to say that areasonable man in the position of the party who opposes unsuccessfullya finding of frustration would certainly have agreed to an implied termbringing it about. I may be allowed to note an example of the artificiality of the theory ofan an implied term given by Lord Sands in Scott & Sons v. Del Sel [1922]S.C. 592 at p. 595: " A tiger has escaped from a travelling menagerie. The" milk girl fails to deliver the milk. Possibly the milkman may be exonerated" from any breach of contract: but even so it would seem hardly reasonable" to base that exoneration on the ground that ' tiger days excepted ' must be" held as if written into the milk contract". I think that there is much force in Lord Wright's criticism in Denny, Mott& Dickson at p. 275: " The parties did not anticipate fully and completely," if at all, or provide for what actually happened. It is not possible, to my" mind, to say that, if they had thought of it, they would have said: ' Well, if" ' that happens, all is over between us '. On the contrary, they would almost" certainly, on the one side or the other, have sought to introduce reservations" or qualifications or compensations ". It appears to me that frustration depends, at least in most cases, not onadding any implied term but on the true construction of the terms which arein the contract read in light of the nature of the contract and of the relevantsurrounding circumstances when the contract was made. There is muchauthority for this view. In British Movietonews Ltd. v. London & DistrictCinemas, Ltd. [1952] A.C. 166 at p. 185 Lord Simon said: " If, on the other" hand, a consideration of the terms of the contract, in the light of the circum-" stances existing when it was made, shews that they never agreed to be bound" in a fundamentally different situation which has now unexpectedly emerged," the contract ceases to bind at that point—not because the court in its" discretion thinks it just and reasonable to qualify the terms of the contract," but because on its true construction it does not apply in that situation ".In Parkinson v. Commissioners of Works [1949] 2 K.B. 632 Asquith, LJ.said (at p. 667): " In each case a delay or interruption was fundamental" enough to transmute the job the contractor had undertaken into a job of a" different kind, which the contract did not contemplate and to which it"could not apply, although there was nothing in the express language of" either contract to limit its operation in this way ". I need not multiplycitations but I might note a reference by Lord Cairns so long ago as 1876 to" additional or varied work so peculiar so unexpected and so different from" what any person reckoned or calculated upon " (Thorn v. The Mayor and 8 Commonalty of London, 1 App. Cas 120 at p. 127). On this view there isno need to consider what the parties thought or how they or reasonable menin their shoes would have dealt with the new situation if they had foreseenit. The question is whether the contract which they did make is, on itstrue construction, wide enough to apply to the new situation: if it is notthen it is at an end. In my view, the proper approach to this case is to take from the arbitrator'saward all facts which throw light on the nature of the contract or whichcan properly be held to be extrinsic evidence relevant to assist in its con-struction and then, as a matter of law, to construe the contract and todetermine whether the ultimate situation as disclosed by the award is oris not within the scope of the contract so construed. The Appellants on 18th March, 1946, sent to the Respondents with theirtender a covering letter. I agree with your Lordships that this letter was notincorporated in the contract of 9th July, 1946, and I do not think that it canbe used in construing this contract. It was simply part of the preliminarynegotiations and we do not know and cannot enquire why it was notincorporated in the contract. The arbitrator has found that both parties " anticipated that there would" be available in the building industry a sufficient labour force and a sufficient" supply of materials to enable the work specified in the agreement to be" carried out substantially within the time stipulated in the agreement".The nature of the contract is such that they must have expected this. Thecontract required the Appellants to complete the work within 8 months andprovided for payment of liquidated damages if the Appellants failed to do sosubject to the surveyor being required in certain events to allow such addi-tional time as he might deem fair and reasonable: and it was clearly of greatimportance to the Appellants that there should be no substantial delaybecause any such delay was bound to add considerably to their costs. Itappears from the arbitrator's findings that the parties did not make theirexpectations known to each other, and I do not think that a finding thatthe parties in fact expected that there would be no substantial delay addsanything material or alters the legal position. The arbitrator then found that the conditions in which the work had to becarried out were different from those anticipated in that at all times there wasa serious shortage of labour and difficulty in obtaining adequate suppliesof bricks and other material. He found that as a result of this shortage andthe consequent delay in completing the work the actual cost to the Appellantsof carrying out the contract was £115,233 whereas the sum paid to themunder the contract was £94,424. The arbitrator has not awarded the whole ofthe difference between these sums. He held that to some extent the Appellantswere themselves to blame and awarded £17,651 as the additional cost andexpense properly and unavoidably incurred by them If the contract continued to apply then the Appellants are not entitledto more than they have already received; but if it was brought to an endthen the Respondents admit that the Appellants are entitled to the sumawarded subject to a very small adjustment. The arbitrator found that "the Respondents accepted the position" and allowed the work to continue until finally completed on 14th" May, 1948, without serious objections by the Respondents". I donot think that that means or was intended by the arbitrator to meanthat at some time while the work was in progress the parties agreedor must be held to have agreed that their contract should no longerapply and that the work should proceed on some other basis. Thereis no finding as to when any such agreement must be held to have been madeor what were its terms and there are no facts found from which such anagreement could be inferred. The Respondents no doubt recognised thatthe delays were not due to the fault of the Appellants: they made no claimfor liquidated damages, and they made no attempt to take the work out ofthe hands of the Appellants as they could have done if the Appellants hadbeen at fault. But that is no ground for inferring an agreement to terminatethe contract and proceed on some different basis. 9 The Appellants' case must rest on frustration, the termination of the con-tract by operation of law on the emergence of a fundamentally differentsituation. Using the language of Asquith, L.J. (as be then was) which I havealready quoted, the question is whether the causes of delay or the delays were" fundamental enough to transmute the job the contractor had undertaken" into a job of a different kind, which the contract did not contemplate and to" which it could not apply ". In most cases the time when the new situationemerges is clear, there has been some particular event which makes all thedifference. It may be that frustration can occur as a result of gradual change,but if so the first question I would be inclined to ask would be when thefrustration occurred and when the contract came to an end. It has beenassumed in this case that it does not matter at what point during the progressof the work the contract came to an end, and that, whatever the time mayhave been, if the contract came to an end at some time the whole of thework must be paid for on a quantum meruit basis. I do not pursue thismatter because the Respondents have admitted that if there was frustrationat any time the Appellants are entitled to the sum awarded. But even so,I think one must see whether there was any tune at which the Appellantscould have said to the Respondents that the contract was at an end and thatif the work was to proceed there must be a new contract, and I cannot findany time from first to last at which they would have been entitled to saythat the job had become a job of a different kind which the contract did notcontemplate. There is a difficulty about a party being entitled to go onand finish the work without raising the question that a new agreement isnecessary and then maintain that frustration occurred at some time whilethe work was in progress, but again I do not pursue that matter because itdoes not arise in view of the course this case has taken. In a contract of this kind the contractor undertakes to do the work for adefinite sum and he takes the risk of the cost being greater or less thanhe expected. If delays occur through no one's fault that may be in the con-templation of the contract and there may be provision for extra time beinggiven: to that extent the other party takes the risk of delay. But he doesnot take the risk of the cost being increased by such delay. It may be thatdelay could be of a character so different from anything contemplated thatthe contract was at an end, but in this case in my opinion the most thatcould be said is that the delay was greater in degree than was to be expected.It was not caused by any new and unforeseeable factor or event: the jobproved to be more onerous but it never became a job of a different kindfrom that contemplated in the contract. Bush v. Whitehaven Trustees appears to me to be a very special case andit must be read in light of the development of the law in later cases. I agreewith your Lordships' comments on it and I can get little assistance from itfor the decision of the present case. I agree that this appeal should bedismissed. Lord Radcliffe MY LORDS, I agree that this appeal fails. Of the two main grounds upon which theAppellants rely the shorter is that which concerns the question whether theirbuilding contract was made subject to a condition as to the availability ofadequate supplies of labour and material by incorporating in its terms therelevant part of a letter from the Appellants to the Respondents dated 18thMarch, 1946. I will deal with that point first. But at the outset I mustremark that if I thought, as I do not, that the Appellants were right in theirargument that such a condition was incorporated, I should not necessarilyconclude from that that they were entitled to succeed in their appeal. Fortheir success would depend upon a further question, What significance shouldbe attached to the words of the condition as part of the whole contract andwhat legal consequences should flow from them? As I believe that your 10 Lordships are at one in thinking that the incorporation claimed never tookplace, I do not think that I need say anything more with regard to this furtherquestion except that it is itself a difficult one upon which some difference ofview has already shown itself in the Courts. The building contract is contained in a written agreement under seal datedthe 9th July, 1946. The agreement itself is quite short and its main purposeis to identify a number of separate documents which, it states, are to " form" and be read and construed as part of this Agreement." These other docu-ments had come into existence for the purpose or during the course of thenegotiations which had proceeded the making of the formal agreement. Thus, early in the year 1946 the Respondents had drawn up Bills of Quan-tities and a Form of Tender which indicated the nature of their requirements,and had invited inspection of their Drawings, Specifications and Conditionsof Contract. Contractors wishing to tender for all or part of the projectedwork were to deliver their tenders on the form prescribed by the 19th March,1946. On the 18th March, the Appellants sent in a signed Tender on the appro-priate form undertaking the erection of (inter alia) 78 houses at GudgeheathLane, Fareham, at a price of £92,425 and within the time limits specified.With it went a covering letter of the same date. As this is the letter whichcontains the alleged contractual term it is desirable to set it out in full. " davis contractors limited 325, Kilburn High Road, London, N.W.618th March, 1946. RL/JEM Clerk of the Council, Fareham Urban District Council, Westbury Manor, Fareham, Hants. dear sir, Re Gudgeheath Lane, Fareham. We have pleasure in enclosing herewith our Tender prepared in accordancewith your Bills of Quantities, and Specifications submitted by your Engineerand Surveyor for One hundred and fifty two houses on four sites. Our tender is subject to adequate supplies of material and labour beingavailable as and when required to carry out the work within the time specified. It is also based on the present published market prices of materials deliveredto site and existing established rates of wages in the various trades for thedistrict. Purchase tax has not been allowed for in our Tender and payment of suchwill form a nett addition to the Contract's sum. Also any variation in priceof labour or materials will form nett additions or omissions to or from theContract's sum, as may be determined by calculation. We have based our price for facings on a p.c. amount of 20s. on the presentquoted price for Fletton bricks delivered Fareham station. This has beennecessary as we have been unable to get firm quotations for facings deliveredto site. Thank you for this opportunity of serving you, and we assure you always ofour best attention. Yours faithfully, For and on behalf of davis contractors ltd.(sd) W. B. W. C. Curd.Director. contracts manager." 11 The Form of Tender which the Respondents prescribed had an Appendixattached to it, bearing the heading " Materials and Goods to be purchased" directly by the Contractor, in respect of which variation of the Contract sum" is desired in accordance with Clause 68a of the Conditions of Contract."There was then a blank space left under two column headings " Materials or" Goods " and " Basic Price." In this blank space the Appellants had writtenthe words " As terms of letter attached dated 18th March, 1946, reference" RL/JEM." There was nothing else in the Appendix except a Clause limitingto some extent the contractor's right to vary the contract sum in respect ofprice variations of materials and goods. As the Arbitrator found in his originalAward, the purpose of the Appendix was " to enable contractors tendering" for work to make a list in that Appendix of all materials or goods which" might be subject to a rise or fall in price so that both parties to the contract" would be protected from the effect of fluctuation of prices ..." Between the 18th March and the date when the formal Agreement wasentered into the Appellants in fact supplied the Respondents with a detailedSchedule of Prices, which was intended to constitute the list of materials andgoods called for by Appendix I and was accepted. No further referenceappears to have been made to the letter of the 18th March. These are the circumstances in which it has to be decided whether thesecond paragraph of this letter formed a qualifying condition incorporatedinto the building contract. As the formal Agreement of 9th July was evidentlyintended to sum up everything that had emerged from the preceding negotia-tions, it is necessary for the Appellants to show that that Agreement somehowcarried into its terms the stipulation contained in that second paragraph.Nor did their argument before your Lordships proceed on any other basis. It is put in two ways. I do not agree with either of them. On the con-trary, I agree with the way that this question was disposed of by LordJustice Parker in the Court of Appeal: but, since the Appellants' argumenton this point commended itself both to the Lord Chief Justice in the Queen'sBench Division and to a majority of the Court of Appeal on the occasion ofeach hearing, it is only right that I should notice it with some particularity. The formal Agreement, as I have said, referred to and incorporated a num-ber of the preliminary documents. These were listed in Clause 2 asfollows: — " (a) The said Tender " (b) The Drawings " (c) The General Conditions of Contract " (d) The Specification " (e) The Bill of Quantities " (f) The Schedule of Rates and Prices (if any)." Now what was the " said Tender'"? The actual form of the words is dueto the only recital of the Agreement, it which it is stated that the Employer" has accepted a Tender by the Contractor for the sum of £92,425 8s. 4d.,"etc. The first way that the Appellants put their case is that the Tenderreferred to is the whole offer made on the 18th March, and that this offerincluded the second paragraph of the covering letter which was intendedas a qualification of the terms of the Form of Tender. My Lords, I think that this argument is a misreading of what the Appellantsand Respondents intended by the formal Agreement. Certainly all the otherdocuments incorporated by Clause 2 are separate named documents which theparties were at some pains to identify by their respective signatures. Every-thing points to the " said Tender" being, similarly, the document calledForm of Tender which the Appellants had signed on the 18th March andforwarded by their letter. Nothing else in fact could properly be referredto as a " Tender " : for there is a contradiction in terms in speaking of aletter which states that " our Tender " is enclosed as if it were itself part ofthat very Tender. As I see it, the truth of the matter is that in forwardingtheir Tender the Appellants proposed a qualification of the expected contractwhich the Respondents did not accept and to which the Appellants did notthemselves return. I do not think it unfair to add the point that if they had, 12 their stipulation could hardly have been left in its existing form which is atonce sweeping and inconclusive. The alternative argument rests upon the fact that the Appendix to theForm of Tender had had written in it by the Appellants a reference to theletter of 18th March. But I do not see how this can avail them with regardto the second paragraph of that letter. For the whole purpose of the Appendixwas to provide a list of materials and goods that were to rank in allowingvariations of the contract sum. In so far as parts of the letter did refer toprices of materials and goods, as indeed some did, I think that it would becorrect to say that those passages formed part of the Form of Tender and, assuch, might have been incorporated in the formal Agreement. I say " might" have been ", because I think that the Arbitrator's finding that the laterSchedule of Prices supplied on 20th May was intended to constitute Appen-dix I of the tender must mean that the original reference to the letter of 18thMarch ceased to have any contractual significance by the time that the formalAgreement was made. But, however that may be, I think it plain that thereference in the Appendix could only bear upon matters relating to theprices of materials and goods and could not possibly have been understood bythe parties as bearing upon the general question of the availability of suppliesof labour and material. The context of the Appendix makes it impossibleto suppose that the reference was intended to introduce the letter of 18thMarch as a whole. If the second paragraph of that letter did not form part of the contractualarrangements, the Appellants' right to claim any payment beyond theoriginal contract sum rests upon the argument that at some date beforecompletion the original contract became frustrated by the continued shortageof the necessary supplies of labour and material and that as from that datethe building work was carried on under a new working arrangement whichadmitted of further payment. The supplemental Award of the Arbitratorwas drawn up on the basis that this argument succeeded. Despite hisfindings I think that the law is against the Appellants on this point andthat the award in their favour cannot be sustained. Before I refer to the facts I must say briefly what I understand to be thelegal principle of frustration. It is not always expressed in the same way, butI think that the points which are relevant to the decision of this case arereally beyond dispute. The theory of frustration belongs to the law of con-tract and it is represented by a rule which the Courts will apply in certainlimited circumstances for the purpose of deciding that contractual obligations,ex facie binding, are no longer enforceable against the parties. The descriptionof the circumstances that justify the application of the rule and, consequently,the decision whether in a particular case those circumstances exist are, Ithink, necessarily questions of law. It has often been pointed out that the descriptions vary from one case ofhigh authority to another. Even as long ago as 1918 Lord Sumner was ableto offer an anthology of different tests directed to the factor of delay alone,and delay though itself a frequent cause of the principle of frustration beinginvoked is only one instance of the kind of circumstance to which the lawattends (see Bank Line Ltd. v. Arthur Capel & Co. [1919] AC 435, 457/460).A full current anthology would need to be longer yet. But the varietyof description is not of any importance so long as it is recognised that eachis only a description and that all are intended to express the same generalidea. I do not think that there has been a better expression of that generalidea than the one offered by Lord Loreburn in F. A. Tamplin Steamship Co.Ltd. v. Anglo-Mexican Petroleum Products Co. Ltd [1916] 2 A.C. 397,403/404. It is shorter to quote than to try to paraphrase it: " A court can" and ought to examine the contract and the circumstances in which it was" made, not of course to vary, but only to explain it, in order to see whether or" not from the nature of it the parties must have made their bargain on the" footing that a particular thing or state of things would continue to exist." And if they must have done so, then a term to that effect will be implied," though it be not expressed in the contract ... no court has an absolving" power, but it can infer from the nature of the contract and the surrounding 13 " circumstances that a condition which is not expressed was a foundation on" which the parties contracted." So expressed, the principle of frustration,the origin of which seems to He in the development of commercial law, is seento be a branch of a wider principle which forms part of the English law ofcontract as a whole. But, in my opinion, lull weight ought to be given to therequirement that the parties " must have made " their bargain on the particu-lar footing. Frustration is not to be lightly invoked as the dissolvent of acontract Lord Loreburn ascribes the dissolution to an implied term of the contractthat was actually made. This approach is in line with the tendency of Englishcourts to refer all the consequences of a contract to the will of those whomade it. But there is something of a logical difficulty in seeing how the partiescould even impliedly have provided for something which ex hypothesithey neither expected nor foresaw; and the ascription of frustration to animplied term of the contract has been criticised as obscuring the true actionof the Court which consists in applying an objective rule of the law of con-tract to the contractual obligations that the parties have imposed upon them-selves. So long as each theory produces the same result as the other, asnormally it does, it matters little which theory is avowed (see British Movie-tone News Ltd. v. London & District Cinemas Ltd. [1952] A.C. 166, 184 perViscount Simon). But it may still be of some importance to recall that, ifthe matter is to be approached by way of implied term, the solution of anyparticular case is not to be found by inquiring what the parties themselveswould have agreed on had they been, as they were not, forewarned. It isnot merely that no one can answer that hypothetical question: it is alsothat the decision must be given " irrespective of the individuals concerned," their temperaments and failings, their interest and circumstances " (HirjiMulji v. Cheong Yue Steamship Co. [1926] A.C. 497 at 510). The legal effectof frustration " does not depend on their intention or their opinions, or even" knowledge, as to the event" (loc cit at 509). On the contrary, it seemsthat when the event occurs the " meaning of the contract must be taken" to be, not what the parties did intend (for they had neither thought nor" intention regarding it), but that which the parties, as fair and reasonable" men, would presumably have agreed upon if, having such possibility in" view, they had made express provision as to their several rights and" liabilities in the event of its occurrence " (Dahl v. Nelson, Donkin & Co.6 App. Cas. 38, at 59 per Lord Watson). By this time it might seem that the parties themselves have become so fardisembodied spirits that their actual persons should be allowed to rest inpeace. In their place there rises the figure of the fair and reasonable man.And the spokesman of the fair and reasonable man, who represents afterall no more than the anthropomorphic conception of justice, is and must bethe Court itself. So perhaps it would be simpler to say at the outset thatfrustration occurs whenever the law recognises that without default of eitherparty a contractual obligation has become incapable of being performedbecause the circumstances in which performance is called for would renderit a thing radically different from that which was undertaken by the contract.Non haec in foedera veni. It was not this that I promised to do. There is, however, no uncertainty as to the materials upon which the Courtmust proceed. " The data for decision are, on the one hand, the terms and" construction of the contract, read in the light of the then existing circum-" stances, and on the other hand the events which have occurred " (Denny,Mott v. Dickson Ltd. & James B. Fraser & Co. Ltd. [1944] AC 265, 274/5,per Lord Wright). In the nature of things there is often no room for anyelaborate enquiry. The court must act upon a general impression of whatits rule requires. It is for that reason that special importance is necessarilyattached to the occurrence of any unexpected event that, as it were, changesthe face of things. But, even so, it is not hardship or inconvenience ormaterial loss itself which calls the principle of frustration into play. Theremust be as well such a change in the significance of the obligation that thething undertaken would, if performed, be a different thing from thatcontracted for. 14 I am bound to say that, if this is the law, the Appellants' case seems tome a long way from a case of frustration. Here is a building contract enteredinto by a housing authority and a big firm of contractors in all theuncertainties of the post-war world. Work was begun shortly before theformal contract was executed and continued, with impediments and minorstoppages but without actual interruption, until the 78 houses contractedfor had all been built. After the work had been in progress for a time theAppellants raised the claim, which they repeated more than once, that theyought to be paid a larger sum for their work than the contract allowed:but the Respondents refused to admit the claim and, so far as appears,no conclusive action was taken by either side which would make the conductof one or the other a determining element in the case. That is not in any obvious sense a frustrated contract. But the Appellants'argument, which certainly found favour with the Arbitrator, is that at somestage before completion the original contract was dissolved because itbecame incapable of being performed according to its true significanceand its place was taken by a new arrangement under which they were entitledto be paid not the contract sum but a fair price on quantum meruit forthe work that they carried out during the 22 months that elapsed betweencommencement and completion. The contract, it is said, was an eightmonths contract, as indeed it was. Through no fault of the parties it turnedout that it took twenty-two months to do the work contracted for. Themain reason for this was that, whereas both parties had expected thatadequate supplies of labour and material would be available to allow forcompletion in eight months, the supplies that were in fact available weremuch less than adequate for the purpose. Hence, it is said, the basis orthe footing of the contract was removed before the work was completed: or,slightly altering the metaphor, the footing of the contract was so changedby the circumstance that the expected supplies were not available that thecontract built upon that footing became void. These are the findings whichthe Arbitrator has recorded in his Supplemental Award. In my view these are in substance conclusions of law: and I do not thinkthat they are good law. All that anyone, arbitrator or Court, can do isto study the contract in the light of the circumstances that prevailed at thetime when it was made and. having done so, to relate it to the circumstancesthat are said to have brought about its frustration. It may be a finding offact that at the time of making the contract both parties anticipated thatadequate supplies of labour and material would be available to enable the con-tract to be completed in the stipulated time. I doubt whether it is: but, evenif it is, it is no more than to say that when one party stipulated for completionin eight months and the other party undertook it each assumed that whatwas promised could be satisfactorily performed. That is a statement of theobvious that could be made with regard to most contracts. I think thata good deal more than that is needed to form a " basis " for the principleof frustration. The justice of the Arbitrator's conclusion depends upon the weight to begiven to the fact that this was a contract for specified work to be completedin a fixed time at a price determined by those conditions. I think that hisview was that, if without default on either side the contract period wassubstantially extended, that circumstance itself rendered the fixed price sounfair to the contractor that he ought not to be held to his original price.I have much sympathy with the contractor: but, in my opinion, if that sortof consideration were to be sufficient to establish a case of frustration, therewould be an untold range of contractual obligations rendered uncertain and,possibly, unenforceable. Two things seem to me to prevent the application of the principle offrustration to this case. One is that the cause of the delay was not anynew state of things which the parties could not reasonably be thought tohave foreseen. On the contrary, the possibility of enough labour andmaterials not being available was before their eyes and could have been thesubject of special contractual stipulation. It was not made so. The otherthing is that, though timely completion was no doubt important to both sides,it is not right to treat the possibility of delay as having the same significance 15 for each. The owner draws up his conditions in detail, specifies the timewithin which he requires completion, protects himself both by a penaltyclause for time exceeded and by calling for the deposit of a guarantee bondand offers a certain measure of security to a contractor by his escalatorclause with regard to wages and prices. In the light of these conditionsthe contractor makes his tender, and the tender must necessarily take intoaccount the margin of profit that he hopes to obtain upon his adventureand in that any appropriate allowance for the obvious risks of delay. Tomy mind, it is useless to pretend that the contractor is not at risk if delaydoes occur, even serious delay. And I think it a misuse of legal terms tocall in frustration to get him out of his unfortunate predicament. The arbitrator had put upon him the duty of making further findingsof fact " relevant to the application of the principle in the case of Bush v." Whitehaven ". This may have been hard upon him, for it implies thatthat decision can be ascribed to one ascertainable principle. In my opinion,it cannot. The judgment of the Court of Appeal applied a different principleof law from that upon which the trial judge's questions to the jury (and theiranswers) were based: and the judgment of the Divisional Court was moreor less evenly balanced between the two. According to the findings of thejury taken together the case was one in which all the work done by Bushhad been done under the original contract; the contract was such that itcarried an implied term that the Whitehaven Trustees should give possessionof the whole site without delay; the delay which had taken place changedthe conditions of the contract to such an extent that the " special provisions "precluding Bush from making any complaint of delay could no longer beapplied ; and Bush was entitled to damages for breach of contract arisingfrom the Trustees' failure to keep the implied term, the damages beingrepresented by the additional cost of the work to him over and above thecontract price. It may be difficult to say by what principle of law the" special provisions " of the contract became inapplicable while the contractitself remained enforceable: but I suppose that judge and jury had in mindthat the parties by their conduct had waived the enforcement of the particularclause. There is nothing out of order in such a finding, so long as the factsproved are clear enough to warrant it, though normally one would expectthem to include some discussion, oral or written, between the parties. Idaresay that everyone felt that rough justice had been done. The Court of Appeal, however, decided the case upon a basis which hadonly a slight resemblance to the findings of the jury. By ignoring all thefindings except that which related to the change in the " conditions of the" contract " and by treating that as if it applied to the contract as a wholeand not merely to whatever was to be understood by the words " specialprovisions ", they arrived at a new view of the facts upon which they thoughtthat a case of frustration could be made out. At some time, apparentlyunknown to and unmarked by the parties concerned, the original contracthad disappeared with all its incidents and obligations and in its place hadbeen set up the legal relationship expressed in Bush's claim (though he hadnot made it) to be paid on the basis of a " quantum meruit ". I should havethought that it would have been much simpler to say, had the findings ofthe jury warranted it, that the parties had abandoned the original contractby mutual consent and substituted for it a new contract containing the sub-stance of the old terms but a reasonable price clause instead of the formerfixed price. But that is not frustration: it is fulfilment with variations. My Lords, I think that Bush v. Whitehaven may be worth rememberingas an instance of what can happen to a case during its passage throughsuccessive Courts, but I do not think it worth recording as an exposition ofany principle of law. In that regard the editors of the Law Reports, whoignored it, showed a sounder judgment than Mr. Hudson, who enshrined it.In so far as it applied the principle of frustration to the facts of the case,the principle was in my view misapplied. In so far as the judgments ofthe Court of Appeal contain general statements as to the law of frustration,I think that the subject has been so fully explored in later cases of higherauthority that the particular exposition is of no real value. I am sincerely 16 sorry if our decision embarrasses builders, who may in some cases havefound in the second volume of Hudson on Building Contracts a way ofmitigating the risks of tenders to which the law did not truly entitle them.But in my view their safety lies in the insertion of explicit conditions in anyfixed price contracts they may undertake; it does not lie in an appeal tothe principle of frustration. Lord Somervell of Harrow MY LORDS, I agree that the words on which the Appellant seeks to rely in the letterof 18th March were not incorporated in the contract. I have had the advantage of reading the opinion which has just been readby my noble and learned friend Lord Reid. I agree with him that it isdesirable to decide what is the proper basis of " frustration ". I also agreewith his conclusion on that matter and I should add nothing except thepossibility of confusion if I sought to restate it in my own words. I therefore turn to its application to the issues in the present appeal.As the senior member of the Court of Appeal which remitted the case tothe arbitrator, I would like to express my regret that we did not givemore assistance to enable him to distinguish the " facts " from his conclusionon them. Fortunately, one or two questions put to counsel in the courseof the argument showed that there was now no conflict as to relevant facts. Contracts to be performed in future are based on expectations. If eachparty is equally well informed as to the data on which expectations mustbe based, it may be said that these expectations are the " basis" or" footing " on which the contract is made. It would, of course, be absurdto suggest that if such expectations are not realised the " basis " has goneand the contract is frustrated. As Lord Sumner said in the Larrinaga case(29 Com. Cas. 1 at p. 18): " In effect most forward contracts can be regarded" as a form of commercial insurance, in which every event is intended to be" at the risk of one party or another." Later he says: " No one can tell" how long a spell of commercial depression may last; no suspense can be" more harrying than the vagaries of foreign exchanges, but contracts are" made for the purpose of fixing the incidence of such risks in advance, and" their occurrence only makes it the more necessary to uphold a contract" and not to make them the ground for discharging it." Under the present contract, was the risk of shortage of skilled labourfixed on the Appellant? A builder who undertakes to finish a building bya certain day is, on the face of it, plainly taking such a risk. There areprovisions in the present contract which re-enforce this construction, wereit necessary to do so. With regard to prices of certain materials and ratesof wages there are what are called escalator clauses. The Appellant wasnot prepared to take the risk of increases in these matters. The parties alsodirected their minds to the possibility of the work not being completed inthe specified time. The Appellant was to pay so much per week indamages. Extra time could, however, be allowed if there was delay bystrikes or if the work was stopped by order of the surveyor. This is tome a somewhat obscure clause, but it is sufficient that there was an exceptionclause for delay which did not cover shortage of labour, and provided onlyfor relief from penalties and not for any extra cost that the delay mightcause the Appellant. The shortage of skilled labour as is shown by theadmitted figures set out in the points of claim was very substantial. Evidencewas called, which may not have been admissible, to show that the expecta-tions were based on statements on behalf of the government as to theprobable availability of skilled labour. A party contracting in the lightof expectations based on data of that or any other kind must make uphis mind whether he is prepared to take the risk of those expectationsbeing disappointed. If not then he will refuse to contract unless protectedby some specific provision. There is no such provision here. The Appellant 17 took the risk under the contract, and it seems to me quite impossible tomaintain that the contract did not apply in the situation as it remained,the expectations on which the estimate was based not having been realised. But for the decision in Bush v. Whitehaven Trustees (2 Hudson's BuildingContracts 4th edn. p. 122) I doubt if the issue of frustration would everhave been raised. I will give my reasons as shortly as I can for thinkingthat that case should not hereafter be citable as a decision relevant tothe law of frustration. The case was fully examined by Cohen, L.J., ashe then was, in Parkinson (Sir Lindsay) & Company Limited v. Commis-sioners of H.M.'s Works and Public Buildings [1949] 2 K.B. 632). The plain-tiffs' claim was for extra expenses incurred on work and labour in that thedefendants had not made the site on which the plaintiffs were to do thework available as required. The delay was substantial and turned a summercontract into a winter contract. The defendants relied on an exceptionclause providing that a failure to make the site available when requiredshould not " vitiate or affect the contract". I think that the jury tookthe view, whether sound in law or not, that the delay was so great thatit ought not to be covered by the exception and that the defendant shouldbe treated as in breach. It is the form of two of the questions left to thejury that led the courts to deal with the case as one of frustration. Thefirst two questions and answers were as follows: — " (1) Was it the duty of the defendants under the contract to be" in a position at the commencement of and at all times during the" contract to give the contractor the use of so much of the site of the" works as might, in the opinion of the engineer, be required to enable" the contractor to commence and continue the execution of the works" in accordance with the contract? A. Yes. " (2) Was the contract made upon the basis that the defendants would" be in a position to act as aforesaid? A. Yes." I doubt if this second question was a proper question to put. It was in anyevent liable to mislead. " Basis " may mean no more than " expectation ".If it means more it is difficult to reconcile questions (1) and (2) withgiving any effect to the exception clause. The fifth question is also difficult." Were the conditions of the contract so completely changed, in consequence" of the defendants inability to hand over the sites of the work as required," as to make the special provisions of the contract inapplicable? A. Yes."This does not suggest that the contract is gone altogether but only thatthe special provisions are inapplicable. The jury, in my view, took thesewords as referring to the exception. Question 8 was as to the " damage" suffered ", and the jury awarded £600 over and above the contract price. It appears that Lord Esher had some doubt as to whether the answerto the fifth question should be taken as a binding finding. Findings byjuries on mixed questions of law and fact are not precedents. That is nodoubt why the case was not reported in any law report. I doubt myself,with respect, whether on the findings of the jury taken with the terms ofthe contract it was possible to treat it as a frustration case. I am clearthat it cannot be regarded as a precedent in the law of frustration as appliedto building or any other contracts. I would dismiss the appeal. (32087)8124—124 35 5/56 D.L./PA/19 BAILII: Copyright Policy | Disclaimers | Privacy Policy | Feedback | Donate to BAILII URL: https://www.bailii.org/uk/cases/UKHL/1956/3.html